The Heath Road Bridge project will begin on Monday, March 19, 2018.  Traffic will be limited to one lane, so please reduce speed and use caution.


The Town of Bremen held a pre-construction meeting with Calderwood Engineering and Hagar Enterprises on December 13, 2017 regarding the Heath Road Bridge Project.

LCN Article on Pre-Construction Meeting

Meeting Minutes

Pre-Construction Meeting Minutes 12-13-2017

Once construction begins, the Town will receive weekly updates from Hagar Enterprises.  The weekly updates will be passed on to all residents on our Town Announcements Email List as well as posted on this website page. 

Below is the anticipated construction schedule.

Hagar Construction Schedule 12-13-2017

If you questions or concerns, please contact the Town Office at 529-5945.